We’re Back.
Progress Update — Winter Hill Triple Decker
After an unexpected early delay, work is fully underway and we are making up lost time.
In just four days, our crew will have framed two levels of this triple decker and on pace to complete rough framing in under two weeks.
This level of ex*****on shows what an experienced and knowledgeable team can accomplish. Watching this frame come together has been a reminder that a GC is only as good as the subcontractors he hires,
The first plate was set on Tuesday, March 17. By the end of the day Friday, March 20, the second-floor exterior walls are expected to be complete.
Windows and roofing are dropping Thursday March 26, by March 31 we’ll be weather tight.
More progress coming soon.
08/19/2025
LET’S GO!!! 🚀
We’re fired up to break ground on our newest project—a ground-up, triple-decker at the top of Winter Hill!
It's been a while since we had the opportunity to tackle a new build, and this one is right in our backyard.
The best part? The Team we are privileged to work with: KDI Architects, Spruhan Engineering, Bruno Bros Plumbing, Blueprints Builders, Zack Ciampa & The Santana Team, H1H2 Capital, and many more.
Stay tuned—this is just the beginning. More updates to come as we bring this project to life!
Collaborators:
ciampa_re
06/03/2025
Private Cambridge condo residence.
Follow-up to our previous post with finished details!🤩
Click here to claim your Sponsored Listing.
Category
Contact the business
Telephone
Website
Address
Somerville, MA
02145
Opening Hours
| Monday | 8am - 4pm |
| Tuesday | 8am - 4pm |
| Wednesday | 8am - 4pm |
| Thursday | 8am - 4pm |
| Friday | 8am - 4pm |