Blitzen Construction LLC
03/25/2025
We are currently three weeks ahead of schedule at Portland’s next Escapology . We have drywall up on one side of each wall while our Low Voltage team installs all the low voltage for the games. We also have our HVAC team finishing up our ducting. Next step is insulation and the rest of drywall. Escapology
03/12/2025
Today was a highly productive day at the build-out! We got three HVAC units installed on the roof and passed the final firewall inspection. Plus, we made solid progress on electrical, low voltage, and ducting.
As we start a new week of construction here is a look back at last week’s progress.