Selvaggi Built
05/23/2026
The unit stays open.
That is not a marketing line. It is an operational commitment that requires a specific sequence to deliver.
Containment sealed to the deck before demo. Negative pressure established and logged. HEPA unit staged and running. Entry and egress protocol confirmed with the charge nurse before the first crew member enters the wing. Noise and vibration schedule coordinated with patient care hours. Debris routes planned to avoid occupied corridors.
Every one of those steps happens before construction starts, not during. Because once you are in an active unit, there is no version of disruption that is acceptable. Patients are there. Staff are working. The facility is licensed and operating. Your construction activity cannot change that.
Zero-disruption protocol is not a feature. It is the price of admission for working in an occupied facility.
05/18/2026
Logged at every shift change.
Negative pressure is not a setup condition. It is an ongoing protocol. In an active healthcare facility, the air pressure relationship between the construction zone and the occupied corridor has to be maintained continuously, not just verified at the start of the day.
We log pressure readings at every shift change. If the HEPA unit drops performance, work stops. If a seal is compromised, it is addressed before the next crew enters. The documentation exists not because a regulator asked for it but because a facility director should be able to pull the log and know, for any hour of any day, that the containment held.
That is the standard in an occupied facility. Everything else is a liability.
05/17/2026
The schedule is built before demo.
The most expensive phase of a healthcare renovation is not construction. It is the one after a problem surfaces in the field that preconstruction should have caught. An RFI that stops three trades. A phasing conflict that forces a weekend shutdown. A lead-time item that was not on order because nobody confirmed the spec in week one.
We build the schedule before we pull permits. Existing conditions are field-verified. Submittals are staged against the phase sequence. Long-lead equipment is identified and ordered before the drawings are even stamped. Every trade knows their sequence, their access window, and their constraints before mobilization.
The schedule is not a Gantt chart handed over at kickoff. It is a living document built from the field up, stress-tested against the facility's operational calendar before a single wall comes down.
That is preconstruction. That is where the project is actually won.
Click here to claim your Sponsored Listing.
Category
Contact the business
Telephone
Website
Address
5100 E. La Palma Avenue Ste 110
Anaheim, CA
92807
Opening Hours
| Monday | 7am - 5pm |
| Tuesday | 7am - 5pm |
| Wednesday | 7am - 5pm |
| Thursday | 7am - 5pm |
| Friday | 7am - 5pm |