π₯QPD Construction
STEPS IN SLAB ON GRADE (SOG) PREPARATION π₯
1. Subgrade Soil Condition
β’ Identify the type of soil (clay, sand, silt, gravel).
β’ Remove organic materials, roots, or soft soil.
β’ Replace weak soil with engineered fill or granular base.
β’ Expansive clay soils need stabilization (lime or cement treatment).
2. Moisture Content
β’ Soil must be at optimum moisture content (OMC) for proper compaction.
β’ Too dry β soil will not bind well.
β’ Too wet β soil becomes unstable or βpumping.β
β’ Water should be added or soil aerated before compaction.
3. Layer Thickness (Lift Thickness)
β’ Soil or gravel should be compacted in layers, not all at once.
β’ Typical lift thickness:
β’ 150β200 mm (6β8 inches) for soil
β’ 200β300 mm (8β12 inches) for granular fill
β’ Each layer must be compacted before adding the next.
4. Compaction Equipment
Choose equipment based on soil type:
Soil Type Recommended Equipment
Clay / cohesive soil Sheepsfoot roller
Sand / gravel Vibratory plate compactor or roller
Small areas Plate compactor or rammer
5. Compaction Standard
β’ Most building slabs require 95% compaction based on the Proctor Compaction Test.
β’ Field verification may use:
β’ Nuclear density test
β’ Sand cone test
6. Subbase or Base Course
Typical materials:
β’ Crushed gravel
β’ Crushed stone
β’ Base course
Functions:
β’ Improves drainage
β’ Distributes load
β’ Prevents capillary water rise.
Typical thickness: 100β150 mm (4β6 inches).
7. Drainage Considerations
β’ Ensure the site has proper slope and drainage.
β’ Standing water weakens compacted soil.
β’ Install perimeter drains or gravel layers if groundwater is high.
8. Proof Rolling
After compaction:
β’ A heavy roller or truck passes over the surface.
β’ If the soil deflects or pumps, it indicates weak spots that must be reworked.
9. V***r Barrier Installation
Before pouring concrete:
β’ Install polyethylene v***r barrier to prevent moisture from rising into the slab.
β’ Usually 6β10 mil plastic sheet.
10. Final Surface Leveling
β’ Ensure the base is level and well graded.
β’ No loose spots before placing reinforcement and concrete. TATAK QUALITY
15/02/2026
Hiring for CEBU CITY PROJECTS βΌοΈ
Click here to claim your Sponsored Listing.
Category
Contact the business
Website
Address
Liloan
6002
Opening Hours
| Monday | 8am - 5pm |
| Tuesday | 8am - 5pm |
| Wednesday | 8am - 5pm |
| Thursday | 8am - 5pm |
| Friday | 8am - 5pm |
| Saturday | 8am - 12pm |