Photos from JLS Engineering Services's post 18/03/2026

Site Progress as of March 16, 2026

Preparation of 2nd floor Beam framing
✅6-16mm main bar (3top, 3bottom)
✅135* stirrup hooks
✅Polypropylene (PP) Board formworks
✅GI Steel shoring

08/03/2026

Heads up! There may be a possible increase in construction material prices in the coming weeks due to supplier price adjustments. This may also affect overall project and contract costs. We appreciate your understanding and will keep everyone posted on any updates.

Photos from JLS Engineering Services's post 25/02/2026

SS14 Home Improvement Project
Two weeks progress ✅

✅ Demolition and Excavation
✅ 4 combined footings poured
✅ 4 concrete columns poured
✅ Wall footings and CHB layering

Photos from JLS Engineering Services's post 10/02/2026

📍Somerset Phase 14, Lancaster New City, Cavite

Start of a new design and build project 🙏