THE PROCESS OF BOREHOLE DRILLING.

STEP 1: HYDROGEOLOGICAL/ GEOPHYSICAL SURVEY:
We employ both Digital and Old methods.
This gives;
✔Borehole depth,
✓ Expected yield
✔Expected Water Quality
TIMELINE: Exercise 1 day, Report 3 Days

STEP 2: DRILLING APPROVALS AND PERMITS:
The necessary approvals includes; ✓Environmental Impact Assessment (EIA)
✔Water Resources Authority (WRA) approval.
✔Water Resources Users Association (WRUA) ✓ Letter of No Objection from the local water provider
✓ County Approvals
TIMELINE: within one month

STEP 3: BOREHOLE DRILLING:
The total cost will be calculated based on the recommendations from the Hydrogeological survey results. This includes;
✓Drilling
✓ Gravels
✓Casing
✓Development
TIMELINE: 5 Days

STEP 4: PUMP TESTING:
Aims to determine the optimum rate at which a borehole should be pumped and yield
TIMELINE: 24 hours

STEP 5: BOREHOLE EQUIPPING AND PUMP INSTALLATION.
This involves installation of submersible pump & motor.
✓pipes
✓ submersible cables,
✓ control panel,
✔Inverter and solar panels (if solar powered).
TIMELINE: For Electricity 1 Days and 3 days for Solar

With availability of resources a borehole can be drilled within 5 to 10 Working days.This includes the drilling,casings, test pumping and water analysis plus pump installation.
Call/Whatsapp for any further clarifications.+265 884 573 815

Photos from Kapos Engineering Group's post 03/12/2023

Water reticulation system in Chiladzulu, talk to us for Solar powered water supply in your area

Want your business to be the top-listed Business in Lilongwe?
Click here to claim your Sponsored Listing.

Telephone

Address


Area 3 Market, Box 96
Lilongwe

Opening Hours

Monday 07:00 - 17:00
Tuesday 07:00 - 17:00
Wednesday 07:00 - 17:00
Thursday 07:00 - 17:00
Friday 09:00 - 17:00