THE PROCESS OF BOREHOLE DRILLING.
STEP 1: HYDROGEOLOGICAL/ GEOPHYSICAL SURVEY:
We employ both Digital and Old methods.
This gives;
✔Borehole depth,
✓ Expected yield
✔Expected Water Quality
TIMELINE: Exercise 1 day, Report 3 Days
STEP 2: DRILLING APPROVALS AND PERMITS:
The necessary approvals includes; ✓Environmental Impact Assessment (EIA)
✔Water Resources Authority (WRA) approval.
✔Water Resources Users Association (WRUA) ✓ Letter of No Objection from the local water provider
✓ County Approvals
TIMELINE: within one month
STEP 3: BOREHOLE DRILLING:
The total cost will be calculated based on the recommendations from the Hydrogeological survey results. This includes;
✓Drilling
✓ Gravels
✓Casing
✓Development
TIMELINE: 5 Days
STEP 4: PUMP TESTING:
Aims to determine the optimum rate at which a borehole should be pumped and yield
TIMELINE: 24 hours
STEP 5: BOREHOLE EQUIPPING AND PUMP INSTALLATION.
This involves installation of submersible pump & motor.
✓pipes
✓ submersible cables,
✓ control panel,
✔Inverter and solar panels (if solar powered).
TIMELINE: For Electricity 1 Days and 3 days for Solar
With availability of resources a borehole can be drilled within 5 to 10 Working days.This includes the drilling,casings, test pumping and water analysis plus pump installation.
Call/Whatsapp for any further clarifications.+265 884 573 815
03/12/2023
Water reticulation system in Chiladzulu, talk to us for Solar powered water supply in your area
Click here to claim your Sponsored Listing.
Category
Contact the business
Telephone
Website
Address
Area 3 Market, Box 96
Lilongwe
Opening Hours
| Monday | 07:00 - 17:00 |
| Tuesday | 07:00 - 17:00 |
| Wednesday | 07:00 - 17:00 |
| Thursday | 07:00 - 17:00 |
| Friday | 09:00 - 17:00 |