Consumed Load = Total Load · Demand Factor:
Consumed Load in KW = 80 · 1 = 80 KW
Consumed Load in KVA = KW/P.F.:
Consumed Load in KVA = 80/0.8 = 100 KVA
Full Load Current = (KVA · 1000) / (1.732 · Voltage):
Full Load Current = (100 · 1000) / (1.732 · 415) = 139 Amp.