Buckets&Bags
11/07/2025
Day 6 & 7
Cladding complete
Bar looking fabulous
Storage cupboard done
Light oak laminate flooring laid by Athena Flooring Hamlet Court Road
04/07/2025
Day 6
Cladding finished and plastering done ready for me to paint pink 🤭
#
18/06/2025
Day 2
The bi-folds have been installed 🚪 🚪🚪
17/06/2025
Day 1
⚡️First fix electrics completed
⚒️ Final strip of the shelving(so@e of these will be repurposed for storage)
🪚Door frames in and ready for the bifolds
15/06/2025
Ready and waiting for the Garden room makeover by
31/05/2025
Thank you Jersey. You have been amazing!! Beautiful beaches, stunning scenery and fabulous food 🇯🇪
Click here to claim your Sponsored Listing.
Category
Contact the business
Address
Split
SS26RS