Work completed this week on our Birkenhead development:
* Water mains manifold completed and connections for all apartments made.
* Electric MCU and cutouts installed for all apartments ready for connection in the coming week.
* 1st and 2nd floor communal areas boarded and plastered.
* 1st and 2nd floor communal areas mist coated.
* Ground floor apartment sound proofed and dry lined.
* 8 x bathrooms and en-suites tiled.
* 11 x bathroom and en-suite floors fitted with LVT
* K-Rend application and beading started.
* Communal fire doors installed.