Biogas Technology In Zambia.
04/06/2026
100m³ Waste Management Project - 15 Miles, Lusaka. Second ring beam = DONE 💪🏾
Update from 15 Miles: Second ring beam = DONE 💪🏾
For those following our journey — the ring beams are key to making the digester strong and long-lasting. Step by step, we’re building a solution that will turn waste into clean cooking gas and organic fertilizer.
Zambia is going green, one digester at a time 🇿🇲
Thank you for cheering us on. More updates coming soon!
01/06/2026
Project Update: 15 Miles 100m³ Biodigester Plant.
Good evening, Biogas Family! 🇿🇲
Project Update: 15 Miles 100m³ Biodigester Plant.
Sharing our current progress on the 100m³ plant at 15 Miles. The team is pushing hard — excavation, civil works, and dome prep are all moving on schedule.
This plant will serve the farm with clean cooking gas and rich bio-fertilizer, cutting costs and emissions.
We’ll keep you posted as we hit the next milestones. Like & share to support local green energy!
30/05/2026
As we mourn this great loss, we stand with the Ngoni Royal Establishment, the bereaved family, and the entire Ngoni people.
May His Majesty Paramount Chief Mpezeni IV rest in eternal peace.
28/05/2026
Day 1
Today, we kicked off interviews for Lead Masons and Masons with our partners SNV Zambia. These are the men and women who’ll help us bring biogas plants to every province in Zambia.
This project means clean cooking fuel, rich fertilizer for farms, and real jobs for skilled builders across the country. And it all starts with getting the right people.
We’re honored to work alongside SNV Netherlands Development Organisation as we scale up sustainable energy solutions.
Watch this space — the team is growing! 🚀