Sigma-Opal Engineering Limited
31/03/2026
Site Images: Structural works
Work in progress
-beams
13/03/2026
Reinforcement placement for the ground-floor slab prior to concrete casting.
13/03/2026
Damp-proof membrane (DPM) installation to protect the structure from ground moisture
10/03/2026
Foundation backfilling in progress as substructure works advance.
06/03/2026
Ground-floor beams after formwork removal.
03/03/2026
Slab formwork and shuttering in progress. We're getting ready for reinforcement placement at the first-floor level.
27/02/2026
"Runners" positioned to receive slab formwork for the first floor.
24/02/2026
Work in progress...
20/02/2026
Recently cast columns with formwork removed, alongside preparation works for the elevator core.
17/02/2026
Column reinforcement works ongoing, with structural steel elements integrated where required by design.
Click here to claim your Sponsored Listing.