Steady progress on the ongoing construction of a Two-Bedroom Apartment (Upstairs Building) at St. Joseph's Catholic Hospital.
Significant milestones have been achieved in the foundation and substructure phase:
Foundation Formwork: 95% complete, with only minor areas pending final adjustments.
Grade/Tie Beams: 85% complete, with remaining sections awaiting final reinforcement checks and concrete placement.
Backfilling Works: 25% completed using approved materials and proper compaction methods.
Our team remains committed to delivering quality, safety, and efficiency at every stage of the project.
14/04/2026
We currently implementing the construction of a two-bedroom upstairs apartment building for St. Joseph's Catholic Hospital, as a Liberian owned construction company supporting improved accommodation and infrastructure within Liberia’s healthcare sector.
Progress Highlights:
•Foundation works are advancing steadily with continued manual excavation of trenches to required dimensions and alignment
•Column base dowel casting is underway, with seven (7) dowels successfully completed during this phase
•All external foundation trenches are now 100% excavated, marking a significant milestone in the project
Quality Focus Areas:
•Precise excavation of column base locations
•Proper alignment and accurate positioning of dowels
•Maintaining required depth and uniformity across all excavated sections
At Frenbenja, we remain committed to delivering durable, high-quality infrastructure that supports national development and community wellbeing.